ESI Pre-Ship Review
Open Items (As of 5/18/99)
Fabrication needing to be done
- Completion of spectrograph alignment (Andy Sheinis)
- Blacken and seal light leaks (Jim W, Matt)
- Baffles (coll,BSW,grating)(Jim W)
- Light seal CCD shutter (Jeff, Matt)
- Attach slit structure to main frame (Jeff)
- Echellette slit masks (Matt, Jeff)
- Low dispersion slit masks (Matt, Jeff
- Aperture stop for echellette masks (Matt) Slit Mask frames (Matt, Jeff L)
- Balance instrument (Matt)
- Add second neon and argon power supplies. (Barry)
- Rework AC elec. box (Barry)
- Modifications drawings for interferences with front and back cladding
- Modifications to grating cell (Jeff)
- Completion of documentation
Required Testing
- Completion of software testing of electro/mech systems (Jim B, Dean T, De C)
- Testing of alarm conditions (De C, Jim B)
- Burn-in test of full up system including intensive imaging (Bob K, De C)
- Complete Y2K compliance testing(CARA, Steve Allen)
Known problems
- Dewar condensation problem (Richard S)
- Imaging mirror miss location at one particular rotation angle (Jim B, Jeff, Andy)
- 0.009" back focus difference (Andy)
- Leaking cell in camera (Andy, Jeff)
- Cu calibration source (Andy)
- Temperature sensors do not read below 0C